Wisconsin District Court Allocates CERCLA Liability for Past and Future Response Costs
In Barclay Lofts LLC v. PPG Industries, Inc., Case No. 20-CV-1694, 2024 WL 4224731 (E.D. Wis. Sept. 18, 2024), a United States District Court in Wisconsin, after deciding several threshold issues under CERCLA, allocated liability for past and future response costs to clean up a contaminated site based upon a detailed analysis of the operational and material handling practices of the potentially responsible parties. The decision offers insights about the facts that a court may find compelling and the factors that a court may apply to reach an equitable CERCLA allocation among responsible parties.