Reluctant to Unbuild, Courts Rule Against Challengers of Already-Completed Energy Projects

December 23, 2019
Zachary J. Koslap
MGKF Litigation Blog

The adage “you can’t put the toothpaste back in the tube” has manifested itself in two recent federal court decisions. Under separate theories, both the Second Circuit and the District Court of the District of Columbia have issued decisions that highlight the difficulty environmental groups faced in challenging energy infrastructure projects that have been completed during the course of litigation.

Read the full blog post